Preparing Fermilab to Carry Out the P5 Plan

Fuente: arXiv
Saved in:
Bibliographic Details
Main Author: Bellettini, Giorgio
Format: Preprint
Published: 2024
Subjects:
Online Access:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1866916497780113408
author Bellettini, Giorgio
author_facet Bellettini, Giorgio
contents In the past several years, Fermi National Accelerator Laboratory (Fermilab) has suffered a number of troublesome setbacks. In some cases, failures to respond effectively have only made things worse, resulting in the current crisis atmosphere at the laboratory. This is reflected in part in the poorly rated performance appraisals (or PEMP) that the DOE provides to the lab every year. Three entities are currently responsible for supporting, managing, operating, and leading the lab: the Department of Energy (DOE), Fermi Research Alliance (FRA), and the Laboratory Director Office. Two recent events provide opportunities for interested parties to reverse the recent decline: the release in December 2023 of the P5 Report and the DOE decision to rebid the Management & Operating (M&O) contract. The P5 Report a decadal update of recommendations for US particle physics, includes an ambitious and positive roadmap for projects and activities at Fermilab. Carrying out the P5 plan successfully, however, will also require addressing many of the other problems currently besetting the lab. The selection of a new M&O contractor is under the responsibility of the Deputy Director for Operations of the DOE Office of Science Dr. Juston Fontaine. A new M&O Contractor would replace FRA and name a new Director effective January 1, 2025. A new management team, one hopes, would be motivated to solve problems and would enjoy a honeymoon period, enabling them to make positive changes more easily. Stimulated by these recent developments, the authors of this document, all present or past employees, convened confidentially in order to collect testimonials on a series of events symptomatic of the lab problems, to provide constructive criticism and offer possible solutions. This document summarizes this work.
format Preprint
id arxiv_https___arxiv_org_abs_2407_13924
institution arXiv
publishDate 2024
record_format arxiv
spellingShingle Preparing Fermilab to Carry Out the P5 Plan
Bellettini, Giorgio
Accelerator Physics
Physics and Society
In the past several years, Fermi National Accelerator Laboratory (Fermilab) has suffered a number of troublesome setbacks. In some cases, failures to respond effectively have only made things worse, resulting in the current crisis atmosphere at the laboratory. This is reflected in part in the poorly rated performance appraisals (or PEMP) that the DOE provides to the lab every year. Three entities are currently responsible for supporting, managing, operating, and leading the lab: the Department of Energy (DOE), Fermi Research Alliance (FRA), and the Laboratory Director Office. Two recent events provide opportunities for interested parties to reverse the recent decline: the release in December 2023 of the P5 Report and the DOE decision to rebid the Management & Operating (M&O) contract. The P5 Report a decadal update of recommendations for US particle physics, includes an ambitious and positive roadmap for projects and activities at Fermilab. Carrying out the P5 plan successfully, however, will also require addressing many of the other problems currently besetting the lab. The selection of a new M&O contractor is under the responsibility of the Deputy Director for Operations of the DOE Office of Science Dr. Juston Fontaine. A new M&O Contractor would replace FRA and name a new Director effective January 1, 2025. A new management team, one hopes, would be motivated to solve problems and would enjoy a honeymoon period, enabling them to make positive changes more easily. Stimulated by these recent developments, the authors of this document, all present or past employees, convened confidentially in order to collect testimonials on a series of events symptomatic of the lab problems, to provide constructive criticism and offer possible solutions. This document summarizes this work.
title Preparing Fermilab to Carry Out the P5 Plan
topic Accelerator Physics
Physics and Society
url https://arxiv.org/abs/2407.13924