contents In 1969 Bromilow observed that the time $T$ to execute a construction project follows a power law scaling with the project cost $C$, $T\sim C^B$ [Bromilow 1969]. While the Bromilow's time-cost model has been extensively tested using data for different countries and project types, there is no theoretical explanation for the algebraic scaling. Here I mathematically deduce the Bromilow's time-cost model from the fractal nature of activity networks. The Bromislow's exponent is $B=1-α$, where $1-α$ is the scaling exponent between the number of activities in the critical path $L$ and the number of activities $N$, $L\sim N^{1-α}$ with $0\leqα<1$ [Vazquez et al 2023]. I provide empirical data showing that projects with low serial/parallel (SP)% have lower $B$ values than those with higher SP%. I conclude that the Bromilow's time-cost model is a law of activity networks, the Bromilow's exponent is a network property and forecasting project duration from cost should be limited to projects with high SP%.
format Preprint
id arxiv_https___arxiv_org_abs_2409_00110
institution arXiv
publishDate 2024
record_format arxiv
spellingShingle Deduction of the Bromilow's time-cost model from the fractal nature of activity networks
Vazquez, Alexei
Physics and Society
Social and Information Networks
In 1969 Bromilow observed that the time $T$ to execute a construction project follows a power law scaling with the project cost $C$, $T\sim C^B$ [Bromilow 1969]. While the Bromilow's time-cost model has been extensively tested using data for different countries and project types, there is no theoretical explanation for the algebraic scaling. Here I mathematically deduce the Bromilow's time-cost model from the fractal nature of activity networks. The Bromislow's exponent is $B=1-α$, where $1-α$ is the scaling exponent between the number of activities in the critical path $L$ and the number of activities $N$, $L\sim N^{1-α}$ with $0\leqα<1$ [Vazquez et al 2023]. I provide empirical data showing that projects with low serial/parallel (SP)% have lower $B$ values than those with higher SP%. I conclude that the Bromilow's time-cost model is a law of activity networks, the Bromilow's exponent is a network property and forecasting project duration from cost should be limited to projects with high SP%.
title Deduction of the Bromilow's time-cost model from the fractal nature of activity networks
topic Physics and Society
Social and Information Networks
url https://arxiv.org/abs/2409.00110