Test results of the LQXFA/B02 and LQXFA/B03 cryo-assemblies for the High Luminosity LHC upgrade

Fuente: arXiv
Enregistré dans:
Détails bibliographiques
Auteurs principaux: Chlachidze, G., Ambrosio, G., Anerella, M., Apollinari, G., Baldini, M., DiMarco, J., Feher, S., Ferracin, P., Nikolic, V., Nobrega, F., Orozco, C., Orris, D., Prestemon, S., Rabehl, R., Stoynev, S., Vouris, A.
Format: Preprint
Publié: 2025
Sujets:
Accès en ligne:
Tags: Ajouter un tag
Pas de tags, Soyez le premier à ajouter un tag!
_version_ 1866909794271494144
author Chlachidze, G.
Ambrosio, G.
Anerella, M.
Apollinari, G.
Baldini, M.
DiMarco, J.
Feher, S.
Ferracin, P.
Nikolic, V.
Nobrega, F.
Orozco, C.
Orris, D.
Prestemon, S.
Rabehl, R.
Stoynev, S.
Vouris, A.
author_facet Chlachidze, G.
Ambrosio, G.
Anerella, M.
Apollinari, G.
Baldini, M.
DiMarco, J.
Feher, S.
Ferracin, P.
Nikolic, V.
Nobrega, F.
Orozco, C.
Orris, D.
Prestemon, S.
Rabehl, R.
Stoynev, S.
Vouris, A.
contents The US High-Luminosity LHC Accelerator Upgrade Project (AUP) is responsible for delivering cryo-assemblies for the Q1/Q3 quadrupole optical components of the High Luminosity LHC upgrade at CERN. Total of 10 cryo-assemblies containing two Nb3Sn quadrupole magnets per cold mass will be delivered within this program. After the successful test of the first pre-series cryo-assembly in 2023, two more cryo-assemblies were tested at Fermilab's horizontal test facility. Production overview and the test results of the LQXFA/B02 and LQXFA/B03 cryo-assemblies are summarized in this paper. After the first test, to increase the capability of the horizontal test facility, various improvements have been made. These improvements are also described in this paper.
format Preprint
id arxiv_https___arxiv_org_abs_2509_14369
institution arXiv
publishDate 2025
record_format arxiv
spellingShingle Test results of the LQXFA/B02 and LQXFA/B03 cryo-assemblies for the High Luminosity LHC upgrade
Chlachidze, G.
Ambrosio, G.
Anerella, M.
Apollinari, G.
Baldini, M.
DiMarco, J.
Feher, S.
Ferracin, P.
Nikolic, V.
Nobrega, F.
Orozco, C.
Orris, D.
Prestemon, S.
Rabehl, R.
Stoynev, S.
Vouris, A.
Accelerator Physics
The US High-Luminosity LHC Accelerator Upgrade Project (AUP) is responsible for delivering cryo-assemblies for the Q1/Q3 quadrupole optical components of the High Luminosity LHC upgrade at CERN. Total of 10 cryo-assemblies containing two Nb3Sn quadrupole magnets per cold mass will be delivered within this program. After the successful test of the first pre-series cryo-assembly in 2023, two more cryo-assemblies were tested at Fermilab's horizontal test facility. Production overview and the test results of the LQXFA/B02 and LQXFA/B03 cryo-assemblies are summarized in this paper. After the first test, to increase the capability of the horizontal test facility, various improvements have been made. These improvements are also described in this paper.
title Test results of the LQXFA/B02 and LQXFA/B03 cryo-assemblies for the High Luminosity LHC upgrade
topic Accelerator Physics
url https://arxiv.org/abs/2509.14369