How Much of the United States Can Still Host New Hyperscale Data Centers? A Constraint-Based Feasibility Analysis

Fuente: arXiv
Enregistré dans:
Détails bibliographiques
Auteur principal: Janosov, Milan
Format: Preprint
Publié: 2026
Sujets:
Accès en ligne:
Tags: Ajouter un tag
Pas de tags, Soyez le premier à ajouter un tag!
_version_ 1866912870654017536
author Janosov, Milan
author_facet Janosov, Milan
contents The rapid expansion of hyperscale data centers, primarily driven by cloud computing and generative AI is placing growing pressure on electricity systems, land, and climate-sensitive infrastructure. While existing maps document where data centers are currently located, a major unanswered question remains: where can hyperscale data centers still be built under present-day physical, infrastructural, and environmental constraints? Here we address this question, focusing on the United States, using a national-scale, constraint-first geospatial framework that infers feasibility from revealed hyperscale siting patterns rather than from demand forecasts or optimization assumptions. By combining power-grid adjacency, environmental limits, land-use constraints, and climatic constraints within a uniform hexagonal spatial system, we estimate the feasible hyperscale hosting capacity. Our presented approaches converge on a limited feasible land envelope, implying a substantial contraction relative to naive land-availability assumptions. Based on observed build-out patterns, we estimate that total physically feasible U.S. hyperscale capacity lies in the tens of gigawatts rather than the hundreds. The results of this piece are intended to support national-scale reasoning about infrastructure feasibility under modern constraints.
format Preprint
id arxiv_https___arxiv_org_abs_2602_02529
institution arXiv
publishDate 2026
record_format arxiv
spellingShingle How Much of the United States Can Still Host New Hyperscale Data Centers? A Constraint-Based Feasibility Analysis
Janosov, Milan
Physics and Society
C.2.4
The rapid expansion of hyperscale data centers, primarily driven by cloud computing and generative AI is placing growing pressure on electricity systems, land, and climate-sensitive infrastructure. While existing maps document where data centers are currently located, a major unanswered question remains: where can hyperscale data centers still be built under present-day physical, infrastructural, and environmental constraints? Here we address this question, focusing on the United States, using a national-scale, constraint-first geospatial framework that infers feasibility from revealed hyperscale siting patterns rather than from demand forecasts or optimization assumptions. By combining power-grid adjacency, environmental limits, land-use constraints, and climatic constraints within a uniform hexagonal spatial system, we estimate the feasible hyperscale hosting capacity. Our presented approaches converge on a limited feasible land envelope, implying a substantial contraction relative to naive land-availability assumptions. Based on observed build-out patterns, we estimate that total physically feasible U.S. hyperscale capacity lies in the tens of gigawatts rather than the hundreds. The results of this piece are intended to support national-scale reasoning about infrastructure feasibility under modern constraints.
title How Much of the United States Can Still Host New Hyperscale Data Centers? A Constraint-Based Feasibility Analysis
topic Physics and Society
C.2.4
url https://arxiv.org/abs/2602.02529